Minety – 149.7MW

Grid code compliance

The Minety BESS project comprises two phases: Phase 1, an existing 99.8 MW installation, and Phase 2, a proposed 49.9 MW extension connecting to the 132 kV network.

Lightning bolt icon
Power Systems
Charging battery sector icon
Battery Energy Storage
Location pin icon
Minety, UK
Client icon
Confidential
Hero Image
Project Overview Image

Project Overview

Grid code compliance

The Minety BESS project comprises two phases: Phase 1, an existing 99.8 MW installation, and Phase 2, a proposed 49.9 MW extension connecting to the 132 kV network.

Project Facts Image

Project Overview

Battery icon

Grid code compliance

Lightning bolt icon

Phase 1, an existing 99.8 MW installation

Gear with circular arrows icon

Phase 2, a proposed 49.9 MW extension connecting to the 132 kV network

Hand holding a leaf sustainability icon
Capacity
149.7MW
Electricity transmission tower icon
Connection
132 kV
Industrial factory icon
Department
Power Systems

DACI Scope of Work

Electrical power module icon
Load flow and Reactive power capability studies
Battery energy storage icon
IEC60909 Studies
Commercial building power supply icon
G5 Issue 5 Harmonic assessment
Computer monitor with security shield icon
P28 Assessment
Lightning bolt energy icon
G99 RMS Dynamic simulation
Connected network nodes icon
Protection co-ordination and Arc flash

Key Project Facts

01

Grid code compliance

A key challenge was to provide the client with clear technical confirmation and confidence regarding the requirements for Neutral Earthing Resistors (NERs), particularly in response to the high single-line-to-ground (SLG) fault levels. In addition, the Phase 2 design required assessment and confirmation of the need for Point-on-Wave (POW) Controlled Switching Devices (CSDs) on the 132 kV incomer breakers supplying the grid transformer. The challenge was therefore to establish the necessity and technical justification for these protection and switching requirements while ensuring compliance with the applicable network and system requirements to support the client long lead delivery items i.e., NER and inclusion of POW CSD.

DACI Solution

Eng response

To proactively address the project requirements, we engaged with the available technical information at an early stage and established the system model ahead of our usual modelling timeline. This allowed the engineering team to identify and assess the key technical requirements early, rather than waiting for the design to be fully developed.

Our internal design team was closely involved throughout the process, with direct collaboration between the modelling and design disciplines while the equipment specifications were being prepared. This ensured that the modelling assumptions, system requirements, and design specifications were aligned from the outset, enabling potential issues to be identified early and providing the client with greater confidence in the proposed requirement NER and POW CSD requirements.

DACI Solution image
Outcome Image

Outcome

A detailed fast track modelling and studies were completed in 2 weeks that included IEC60909 assessment, NER assessment and P28 transformer energisation including the report which was used as an evidence to finalize the requirement of the NER and POW CSD. In addition to this, the team proactive took responsibility to finalize the specification of the earthing auxiliary transformer which is now in manufacturing. The remaining studies are in progress.

related case study

Battery Energy Storage

SUNDON – 49.9MW BESS

One of the Medium Voltage (MV) skids had a different DC/AC configuration, introducing additional modelling complexity that had to be accurately represented and consistently captured across all studies.

Read Case Study
Battery Energy Storage

Drum Farm – 49.9MW BESS

The OEM RMS and EMT models provided to the customer for plant-level model development exhibited significant performance and stability issues.

Read Case Study

Ready to Build Your Next Critical Energy infrastructure project ?

Let's Collaborate deliver resilient, future ready solutions.

Get in Touch
Hands sketching architectural plans with pencil and ruler on a desk with calculator nearby.