DACI was appointed at an early design stage to act as the utilities design house, supporting the M&E consultant in preparing accurate technical information for tender issue and the Gateway 2 submission under the Building Safety Act.
The developer required robust and coordinated utilities information to ensure compliance and avoid delays within the statutory approval process.
DACI worked closely with the M&E consultant to:
Provide accurate utility design information
Confirm connection parameters and infrastructure requirements
Ensure technical coordination aligned with tender documentation
- Support the Gateway 2 submission with compliant and complete data
Our early involvement ensured that utilities information was robust, coordinated, and suitable for regulatory review.


- Accurate and compliant information submitted at Gateway 2
- Reduced risk of rejection under the Building Safety Act
- Avoided potential 20-week resubmission delay
- Provided confidence and clarity for tender and delivery stages
Early engagement ensured the development was supported with the correct technical detail at a critical approval stage, protecting both programme and compliance.

Design development for a high-capacity EV bus depot charging scheme at Merton Bus Garage.
.png)
Design of a capacity-constrained EV charging scheme where the proposed charging infrastructure required significantly more power than the available network capacity.
.png)
DACI provided multidisciplinary design for the 120 MW Iron Acton battery energy storage system, including its 132 kV National Grid connection, and developed a non-standard bonding solution that avoided a full cable replacement.