Devilla Wood - BESS

Recovering and de-risking a 500 MW grid-scale storage design, mid-construction, under acute programme pressure.

DACI Utilities Engineering Consultancy was appointed to Devilla Wood (EHV-0170), a 500 MW / ~1 GWh grid-scale Battery Energy Storage System connecting to SP Transmission (SPEN) at 275 kV.

Lightning bolt icon
EHV
Charging battery sector icon
Battery Energy Storage
Location pin icon
Devilla Wood, Scotland, UK
Client icon
Confidential
Hero Image
Project Overview Image

Project Overview

Design Recovery and Multidiscipline Delivery

DACI Utilities Engineering Consultancy was appointed to Devilla Wood (EHV-0170), a 500 MW / ~1 GWh grid-scale Battery Energy Storage System connecting to SP Transmission (SPEN) at 275 kV.

DACI joined mid-programme, after civil works had already begun on site and the previous design team had been stood down. DACI assumed responsibility for the full electrical, cabling, civil and power system design: validating the inherited work, flagging and resolving a series of significant defects, and delivering a complete, compliant and adoptable design without disrupting the live construction sequence.

Project Facts Image

Project Overview

Battery icon

500 MW / ~1 GWh grid-scale BESS

Lightning bolt icon

275 kV connection to SP Transmission (SPEN)

Gear with circular arrows icon

275 kV AIS substation: 1 incomer bay, 3 outgoing bays

Leaf icon

Engaged mid-construction, following removal of the previous designer

Hand holding a leaf sustainability icon
Capacity
500 MW / ~1 GWh grid-scale BESS
Electricity transmission tower icon
Connection
275 kV to SP Transmission (SPEN)
Industrial factory icon
Location
Devilla Wood, Scotland, UK

DACI Scope of Work

Electrical power module icon
Cable design: HV / MV / LV sizing, routing and thermal and cyclic rating
Battery energy storage icon
Electrical primary design: 275 kV AIS substation, SGTs and bay layouts
Commercial building power supply icon
Electrical secondary design: protection, control and SCADA
Computer monitor with security shield icon
Civil design: cable trough and cable support structure design
Lightning bolt energy icon
Power system studies: load flow, fault level and protection coordination
Connected network nodes icon
Design validation & assurance: review of inherited scopes and multidiscipline interface coordination

Critical Obstacles

DACI inherited a part-complete design of inconsistent quality while construction was already live on site. The task was to take engineering ownership of work it had not originated: assure what was sound, expose what was not, and complete a compliant design at pace, without holding up the site.

01

[Critical Risk] Mid-construction takeover

Previous designers removed with civil works already underway; DACI validated inherited scopes and adopted full design responsibility under live-site conditions.
02

[Critical Risk] 275 kV clearance breaches

The inherited 275 kV AIS layout carried multiple electrical and safety clearance non-compliances. DACI re-engineered the arrangement to compliant phase and earth clearances.
03

[High Priority] Compressed programme

Multiple disciplines had to advance concurrently under aggressive deadlines, with no tolerance for sequential delay between workstreams.
04

[High Complexity] Site-wide layout clashes

The overall site layout carried numerous spatial clashes and coordination gaps across disciplines, requiring a full re-coordination of the arrangement.
05

[Design Gap] Protection scheme deficiencies & undersized LV/backup supplies

The inherited protection design was below standard and omitted several key areas; DACI redeveloped the scheme to close the gaps and meet grid requirements. LV sizing was also inadequate and significantly underestimated UPS, standby generation and backup supply demand, so DACI re-sized the LV system and resilient supplies.

DACI Solution

Engineering Response

Rather than restart the design, DACI ran a structured validation across every inherited scope, isolating defects early and ranking them by construction impact. Corrected and completed designs were then progressed in parallel, so site works continued while design gaps were closed behind them.

  • Independent design validation across all inherited scopes
  • 275 kV layout re-engineered to compliant clearances
  • Full site-layout clash resolution and re-coordination
  • Protection scheme redeveloped to close omissions
  • LV, UPS, standby generation and backup supplies re-sized
  • Disciplines sequenced to construction priority to protect the programme
DACI Solution image
Outcome Image

Outcome

DACI resolved every inherited issue and delivered a complete, compliant, adoptable design, running ahead of programme on most workstreams, several by over a month, despite joining mid-construction.

Wider Impact

Supporting the UK's Low-Carbon Future

Devilla Wood adds 500 MW / ~1 GWh of flexible grid-scale storage at 275 kV transmission level, supporting network stability and the integration of large-scale renewable generation.

The design assurance and recovery methodologies proven here are directly transferable to other distressed and time-critical BESS and transmission schemes across the UK.

  • Enables large-scale renewable integration at transmission level
  • Improves grid stability and flexibility across the network
  • Supports UK and Scottish decarbonisation and net-zero objectives
  • Demonstrates DACI's design assurance and recovery capability
  • Delivered ahead of programme on most workstreams
Wider Impact Image
Conclusion Image

Conclusion

Technical Expertise, Delivered.

Devilla Wood demonstrates DACI's ability to step into a distressed, mid-construction design, take full engineering ownership across disciplines, and recover it to a compliant, high-performing outcome under acute time pressure.

DACI Utilities Engineering Consultancy · EHV Department · Project EHV-0170

related case study

Battery Energy Storage

Iron Acton Battery Energy Storage System (BESS)

DACI Utilities Engineering Consultancy played a leading role in the delivery of the Iron Acton Battery Energy Storage System (BESS), a 120MW grid-scale development designed to support network stability and enable the integration of renewable energy at transmission level.

Read Case Study
Substation & Transmission

Windyhill Case Study

DACI played a pivotal role in supporting Kirby's in the early stages of The Windyhill substation which is currently in the process of being retrofitted to a 275kV Substation.

Read Case Study

Ready to Build Your Next Critical Energy infrastructure project ?

Let's Collaborate deliver resilient, future ready solutions.

Get in Touch
Hands sketching architectural plans with pencil and ruler on a desk with calculator nearby.