Windyhill Case Study

A Phased 4D BIM model for a feasibility scheme at LOD200 containing two design options

DACI played a pivotal role in supporting Kirby's in the early stages of The Windyhill substation which is currently in the process of being retrofitted to a 275kV Substation.

Lightning bolt icon
EHV
Charging battery sector icon
Substation & Transmission
Location pin icon
Windyhill, UK
Client icon
Confidential
Hero Image
Project Overview Image

Project Overview

DACI played a pivotal role in supporting Kirby's in the early stages of The Windyhill substation which is currently in the process of being retrofitted to a 275kV Substation. The feasibility study was ordered by SPEN to proactively identify potential issues with a further upgrade to 400kV Substation.

A Phased 4D BIM model for a feasibility scheme at LOD200 containing two design options.

Project Facts Image

Project Overview

Battery icon

A model of the existing site as it was at the beginning of the project.

Lightning bolt icon

A model of what the site would look like following the current set of 275kV works

Gear with circular arrows icon

2 different Design options for the upgrade to a 400kV substation

Leaf icon

All phased correctly and within the same model.

Hand holding a leaf sustainability icon
Voltage
275kV to 400kV
Electricity transmission tower icon
Deliverable
Phased 4D BIM model at LOD200
Industrial factory icon
Stage
Feasibility

DACI Scope of Work

Electrical power module icon
Existing Site Terrain Model
Battery energy storage icon
Existing and Proposed GIS Hall Structures and Envelope
Commercial building power supply icon
Existing 275kV and 132kV Legacy Asset Model
Computer monitor with security shield icon
New 400kV GIB Routing and Supports, and Electrical Equipment and Foundations (CVT, SA, PI, ES)
Lightning bolt energy icon
New Cable Trenching and Routing, and New Earthing Grid
Connected network nodes icon
Transformer Integration (400kV to 275kV / 400kV to 132kV), and Coordination and Clash Detection

Obstacles

Early in the project issues were identified with the provided point cloud survey information which was delayed in its delivery and additionally didn't contain the required level of detail especially with regards to cable trenching and ducting. This pushed the programme and started the project off on the wrong foot.

01

Point Cloud Survey Information

Early in the project issues were identified with the provided point cloud survey information which was delayed in its delivery and additionally didn't contain the required level of detail especially with regards to cable trenching and ducting. This pushed the programme and started the project off on the wrong foot.
02

BIM Concepts and Project Management

Due to the lack of understanding in the kirby project management team when it comes to BIM concepts DACI had to tack a leading role in meetings with SPEN especially in the area of timelines, level of details and model expectations early in the project.
03

Ducting and Trenching

There is a dense network of ducting and trenching on the site due to the previous and current works as such this led to a large number of drawings with conflicting information around the positioning of these.
04

Information Consolidation

A significant amount of work was required to consolidate all the information past and present into a usable model.
Outcome Image

Outcome

DACI was able to steer the project back on course despite the initial setbacks

  • We delivered a total of 18 drawings and a 4D Model.
  • DACI through meetings were able to control the scope slipping through regular meeting and were able to complete a model to previously agreed timeframes with only minimal comments and changes required from SPEN and Kirby's
  • SPEN were very pleased with the level detail contained within the model.

Wider Impact

Technical Expertise

Windyhill is DACI's Breakout project not just in 400kV but also in BIM Modelling.

With BIM becoming a mainstay of national infrastructure projects adoption of BIM will become a more necessary step to stay competitive into the future. Windyhill demonstrates that the internal expertise are already in place to actively take charge of these types of projects and deliver projects to a high level.

Wider Impact Image

related case study

Battery Energy Storage

Devilla Wood - BESS

DACI Utilities Engineering Consultancy was appointed to Devilla Wood (EHV-0170), a 500 MW / ~1 GWh grid-scale Battery Energy Storage System connecting to SP Transmission (SPEN) at 275 kV.

Read Case Study
Battery Energy Storage

Iron Acton Battery Energy Storage System (BESS)

DACI Utilities Engineering Consultancy played a leading role in the delivery of the Iron Acton Battery Energy Storage System (BESS), a 120MW grid-scale development designed to support network stability and enable the integration of renewable energy at transmission level.

Read Case Study

Ready to Build Your Next Critical Energy infrastructure project ?

Let's Collaborate deliver resilient, future ready solutions.

Get in Touch
Hands sketching architectural plans with pencil and ruler on a desk with calculator nearby.