Walton Road

Designing a phased potable water network for 1,961 dwellings

DACI designed a potable water network for a major development in Drakelow, supporting 1,961 homes and commercial facilities across four phases, in line with South Staffs Water’s adoption requirements.

Lightning bolt icon
Multi-Utility
Charging battery sector icon
Residential Development
Location pin icon
Drakelow, Burton upon Trent
Client icon
Confidential
Hero Image
Project Overview Image

Project Overview

DACI Utilities Engineering Consultancy was appointed by the ICP to design the potable water network for the Walton Road development in Drakelow, Burton upon Trent. It comprises 1,961 dwellings and commercial facilities, delivered across four phases by multiple developers.

The network was designed for adoption by the water company under its NAV arrangement, following South Staffs Water's Design and Construction Specification (D&CS) and technical requirements.

‍

Project Facts Image

Project Facts

Battery icon

1,961 dwellings and commercial facilities across four phases

Lightning bolt icon

EPANET modelling at 101 litres per person per day

Gear with circular arrows icon

355mm HPPE feed from the A38 trunk main, with 225mm HPPE resilience main

Leaf icon

NAV adoption meeting South Staffs Water requirements

Hand holding a leaf sustainability icon
Development
1,961 Dwellings
Electricity transmission tower icon
Phases
Four (PH1 to PH4)
Industrial factory icon
Location
Drakelow, Burton upon Trent

DACI Scope of Work

Electrical power module icon
Full potable water network design (PH1–PH4)
Battery energy storage icon
EPANET hydraulic modelling and calculations
Commercial building power supply icon
Temporary connection and permanent supply resilience
Computer monitor with security shield icon
Phased PE and barrier pipework design (63–250mm)
Lightning bolt energy icon
AMR metering, boundary boxes and service connections
Connected network nodes icon
Contamination risk management and adoption compliance

Engineering Challenges: Critical Obstacles

The project presented a demanding combination of large-scale phased delivery, supply coordination, and ground and adoption constraints, each requiring precise, coordinated engineering responses.

01

Scale Large-Scale Phased Development

A network for 1,961 dwellings and commercial facilities across four phases, with multiple developers and different construction programmes.
02

Hydraulic Performance Pressure Requirements

Demonstrating satisfactory performance under full-development demand, while meeting minimum pressure, maximum velocity and headloss criteria.
03

Supply Strategy Temporary and Permanent Supply

Serving the first 250 properties from a temporary 6-inch AC main while integrating the permanent feed and resilience main as the development progresses.
04

Site Conditions Contamination and Diversions

Contamination in PH1 and PH2 required barrier pipe, while South Staffs Water diversionary works allowed for two new S278 roundabouts.
05

Compliance Adoption and Technical Standards

Satisfying both the water company's NAV adoption requirements and South Staffs Water's standards, including metering, service routing, hydrants and approved materials.

DACI Solution

DACI developed a comprehensive engineering solution combining detailed hydraulic modelling, phased network infrastructure and coordinated supply arrangements, providing a reliable water supply throughout the phased construction programme.

A network-wide EPANET model of all 1,961 properties used 101 l/p/d, four occupants per household and a peak flow factor of 2.25, run at a conservative 35mH source pressure.

  • Network-wide EPANET hydraulic model
  • Temporary-to-permanent phased supply strategy
  • Barrier pipe specified for PH1 and PH2
  • Coordinated NAV and South Staffs Water adoption requirements
DACI Solution image
Outcome Image

Outcome

The submitted hydraulic calculations demonstrate that the proposed potable water network achieves the design criteria specified by South Stas Water (SSW) under the modelled full-development demand scenario.

The network operates within the velocity and headloss limits while keeping pressure above the minimum requirement. The design conclusion recommends retaining the proposed mains sizing for the approval and construction stages, in line with the Code of Practice for the Self-Laying of Water Mains and Services, England and Wales

Wider Impact

The Walton Road project demonstrates DACI's ability to deliver coordinated utility engineering for large-scale residential developments, with multiple developers and complex infrastructure requirements.

A staged supply strategy and resilient network layout give the development a coordinated basis to progress through approval and construction.

  • Coordinated layout for 1,961 dwellings, designed for phased construction and future connections
  • Detailed modelling informs pipe sizing under full-development demand
  • Staged supply serves the first 250 properties while the permanent feed is brought into operation
  • Approved barrier pipe specified where ground contamination was identified
  • NAV and South Staffs Water requirements met in one engineering submission
Wider Impact Image
Conclusion Image

Conclusion

DACI Utilities Engineering Consultancy Ltd successfully completed the potable water network design for the Walton Road development, comprising 1,961 dwellings and commercial facilities.The project demonstrates DACI's capability to deliver complex utility engineering through detailed hydraulic modelling, phased infrastructure planning, temporary and permanent supply coordination, and the integration of technical adoption requirements. The hydraulic results show integration of technical adoption requirements. The hydraulic results show the network performing within the specified design limits, giving thedevelopment a coordinated basis to progress through approval andconstruction.

related case study

Battery Energy Storage

Minety

The Minety BESS project comprises two phases: Phase 1, an existing 99.8 MW installation, and Phase 2, a proposed 49.9 MW extension connecting to the 132 kV network.

Read Case Study
Residential Development

Residential Development

DACI was appointed to deliver the coordinated multi-utility design for a residential development requiring fully compliant electrical and water infrastructure for adoption under IDNO and NAV frameworks.

Read Case Study
Residential Development

Former Marchon

DACI was appointed at an early design stage to review and develop the electrical design for Phase 1 of a 48-dwelling residential scheme.

Read Case Study

Ready to Build Your Next Critical Energy infrastructure project ?

Let's Collaborate deliver resilient, future ready solutions.

Get in Touch
Hands sketching architectural plans with pencil and ruler on a desk with calculator nearby.