.png)
Grid code compliance
The Minety BESS project comprises two phases: Phase 1, an existing 99.8 MW installation, and Phase 2, a proposed 49.9 MW extension connecting to the 132 kV network.

High fault levels, uncertain long-lead protection requirements, and a compressed decision timeline meant technical justification was needed well ahead of the design being fully developed.
To proactively address the project requirements, we engaged with the available technical information at an early stage and established the system model ahead of our usual modelling timeline. This allowed the engineering team to identify and assess the key technical requirements early, rather than waiting for the design to be fully developed.
Our internal design team was closely involved throughout the process, with direct collaboration between the modelling and design disciplines while the equipment specifications were being prepared. This ensured that the modelling assumptions, system requirements, and design specifications were aligned from the outset, enabling potential issues to be identified early and providing the client with greater confidence in the proposed requirement NER and POW CSD requirements.
.png)
.png)
A detailed fast track modelling and studies were completed in 2 weeks that included IEC60909 assessment, NER assessment and P28 transformer energisation including the report which was used as an evidence to finalize the requirement of the NER and POW CSD. In addition to this, the team proactive took responsibility to finalize the specification of the earthing auxiliary transformer which is now in manufacturing. The remaining studies are in progress.
.png)
DACI played a pivotal role in supporting Kirby's in the early stages of The Windyhill substation which is currently in the process of being retrofitted to a 275kV Substation.
.png)
Design of a capacity-constrained EV charging scheme where the proposed charging infrastructure required significantly more power than the available network capacity.
.png)
DACI Utilities Engineering Consultancy delivered the civil and structural design for the 132 kV substation serving a combined solar and battery storage development at Long Pasture, near Darlington, County Durham.
Let's Collaborate deliver resilient, future ready solutions.

We'd like to use analytics and advertising cookies to see how people use this website and to measure our LinkedIn campaigns. They only run if you accept. See our Privacy Policy.