Former Marchon Case Study

Challenging an LV connection to secure a compliant HV solution

DACI was appointed at an early design stage to review and develop the electrical design for Phase 1 of a 48-dwelling residential scheme.

Lightning bolt icon
HV
Charging battery sector icon
Residential Development
Location pin icon
Former Marchon
Client icon
Confidential
Hero Image
Project Overview Image

Project Overview

DACI was appointed at an early design stage to review and develop the electrical design for Phase 1 of a 48-dwelling residential scheme. Following receipt of the Distribution Network Operator (DNO) Point of Connection (POC) offer, the client required a detailed technical assessment and compliant design submission to ensure the proposed connection was suitable for the development.

Project Facts Image

Project Facts

Battery icon

Phase 1: 48 dwellings

Lightning bolt icon

Future Phase 2: 280 dwellings

Gear with circular arrows icon

Service: Point of connection submission & early design submission

Leaf icon

Client: Confidential

Hand holding a leaf sustainability icon
Service
Point of connection & early design submission
Electricity transmission tower icon
Phase 1
48 dwellings
Industrial factory icon
Phase 2 (future)
280 dwellings

The Challenge

01

LV point of connection offered

The Distribution Network Operator (DNO) issued a Low Voltage (LV) Point of Connection (POC) for Phase 1.
02

Voltage drop beyond acceptable limits

Detailed engineering checks showed that, due to the length of run from the LV POC to the furthest dwellings, voltage drop would exceed acceptable limits. The proposed solution was therefore not compliant and posed a significant delivery risk.
03

Redesign, delay and cost risk

If progressed, the LV solution would likely have resulted in redesign during construction, programme delays, and cost variations and abortive works.

DACI Solution

1. Formal challenge of the LV point of connection

DACI formally challenged the LV POC with the DNO, providing technical justification and requesting a High Voltage (HV) POC to ensure compliance and resilience.

2. Phase 2 infrastructure alignment

At the same time, we reviewed the wider development proposals and considered the future 280-dwelling Phase 2. We assessed whether extending the HV network to a strategically positioned substation could potentially serve both phases, creating a more cost-effective long-term solution.

DACI Solution image
Outcome Image

Outcome

  • Secured a compliant HV solution for Phase 1
  • Eliminated voltage drop and compliance risk
  • Considered infrastructure alignment for future Phase 2
  • Provided a detailed, workable design for comparable contractor pricing
  • Prevented programme delay and late-stage design changes
Conclusion Image

Conclusion

Early engagement enabled DACI to challenge the initial DNO proposal and secure a robust, deliverable solution before the development progressed.

related case study

Microgrid & Distribution

Wilfred Way Case Study

Design coordination for a microgrid site that initially came in as a HV metered scheme.

Read Case Study
EV Charging Infrastructure

EV Charging Infrastructure Enabled Through Non-Standard Elevated Substation Design and Flood Resilience

Design development for a high-power EV charging infrastructure scheme at Booths Keswick.

Read Case Study
EV Charging Infrastructure

Merton Case Study

Design development for a high-capacity EV bus depot charging scheme at Merton Bus Garage, London.

Read Case Study

Ready to Build Your Next Critical Energy infrastructure project ?

Let's Collaborate deliver resilient, future ready solutions.

Get in Touch
Hands sketching architectural plans with pencil and ruler on a desk with calculator nearby.