The Client had received a Point of Connection (POC) offer from the Distribution Network Operator (DNO) which required acceptance within a fixed timeframe to secure electrical capacity for the development.
A compliant design submission was required within 30 days of acceptance. DACI was appointed to prepare and submit the design to ensure the capacity was retained and the offer did not lapse.
Failure to accept the POC within the expiry period would have resulted in:
DACI mobilised immediately to review the DNO offer and produce a compliant electrical design within the required 30-day window.
We coordinated the necessary technical information, prepared the formal design submission, and ensured all requirements were met to allow timely acceptance of the POC.


- Electrical capacity secured within the deadline
- Avoided reapplication costs and potential loss of capacity
- Mitigated risk of increased off-site infrastructure costs
- Maintained programme certainty for the development
Early engagement ensured the connection offer was protected, safeguarding both cost and delivery for the client.

DACI was appointed to deliver the coordinated multi-utility design for a residential development requiring fully compliant electrical and water infrastructure for adoption under IDNO and NAV frameworks.
.png)
Design development for a high-power EV charging infrastructure scheme at Booths Keswick.
.png)
Design coordination for a microgrid site that initially came in as a HV metered scheme.
Let's Collaborate deliver resilient, future ready solutions.

We'd like to use analytics and advertising cookies to see how people use this website and to measure our LinkedIn campaigns. They only run if you accept. See our Privacy Policy.