Warrington Road

Early Utilities Design Engagement

The client received a DNO Point of Connection (POC) offer requiring acceptance within a fixed timeframe, followed by a compliant design submission within 30 days.

Lightning bolt icon
Consultancy
Charging battery sector icon
Residential Development
Location pin icon
Warrington
Client icon
Confidential
Hero Image
Project Overview Image

Project Overview

The Client had received a Point of Connection (POC) offer from the Distribution Network Operator (DNO) which required acceptance within a fixed timeframe to secure electrical capacity for the development.

A compliant design submission was required within 30 days of acceptance. DACI was appointed to prepare and submit the design to ensure the capacity was retained and the offer did not lapse.

‍

Hand holding a leaf sustainability icon
Service
Early Utilities Design Engagement
Electricity transmission tower icon
Development
162 Residential scheme
Industrial factory icon
Location
Warrington

Engineering Challenges

Failure to accept the POC within the expiry period would have resulted in:

01

New Quotation and Application Costs

The need to submit a new application and pay for a replacement quotation.
02

Risk of Losing Electrical Capacity

The possibility that the previously offered electrical capacity would no longer be available.
03

Alternative Point of Connection

The potential need to secure an alternative POC located further away from the development site.
04

Increased Costs and Delays

Additional infrastructure costs and potential delays to the overall project programme.

DACI Solution

Our Approach

DACI mobilised immediately to review the DNO offer and produce a compliant electrical design within the required 30-day window.

We coordinated the necessary technical information, prepared the formal design submission, and ensured all requirements were met to allow timely acceptance of the POC.

‍

DACI Solution image
Outcome Image

Outcome

Outcome

- Electrical capacity secured within the deadline

- Avoided reapplication costs and potential loss of capacity

- Mitigated risk of increased off-site infrastructure costs

- Maintained programme certainty for the development

Early engagement ensured the connection offer was protected, safeguarding both cost and delivery for the client.

‍

related case study

Residential Development

Residential Development

DACI was appointed to deliver the coordinated multi-utility design for a residential development requiring fully compliant electrical and water infrastructure for adoption under IDNO and NAV frameworks.

Read Case Study
EV Charging Infrastructure

Booths Keswick

Design development for a high-power EV charging infrastructure scheme at Booths Keswick.

Read Case Study
Microgrid & Distribution

Wilfred Way

Design coordination for a microgrid site that initially came in as a HV metered scheme.

Read Case Study

Ready to Build Your Next Critical Energy infrastructure project ?

Let's Collaborate deliver resilient, future ready solutions.

Get in Touch
Hands sketching architectural plans with pencil and ruler on a desk with calculator nearby.